Project |
Project Name/Description |
Status |
Completed |
STREETS, SIDEWALKS, BRIDGES (S) |
|||
2017-S6 |
South St - Northbrook to City Limits |
Complete |
Sep |
2017-S7 |
Avon Street - All |
Complete |
Sep |
2017-S8 |
Northbrook - South to Carom Circle |
Complete |
Sep |
2017-S9 |
S. Jefferson - Oak Street to Kipp Road |
Cannot begin construction before June 9 per contract. Pre-Con meeting will be held in May. |
|
2017-S10 |
Sidewalk Program - Summerwood |
Project advertised. Bid opening date is January 29 |
|
2018-S1 |
MDOT- Temple Street Safety Grant |
Project is funded for FY19 (Oct. 1- Sept. 30). Working on revisions for MDOT submittal. |
|
2018-S32 |
Columbia - Cedar to US 127 |
Complete |
Sep |
UTILITIES: SANITARY SEWER, STORM WATER, AND WATER DISTRIBUTION (U) |
|||
2018-U1 |
Utilities for Properties on Kipp Road |
Complete |
Sep |
2017-U3.2 |
Waste Water Treatment Plant Upgrades |
Complete |
Oct |
2017-U3.3 |
Design of the New DPW Facility |
After 2017-U3 |
|
2017-U6 |
Abandon Wells by Airport |
Project on hold; filed FAA permit to do work – up to 45-day response period. |
|
2017-U9 |
Northbrook - South to Carom Circle |
Complete |
Sep |
2017-U10 |
S. Jefferson - Oak St to Kipp Road |
See 2017-S9 |
|
2017-U12 |
300,000 G Storage Tank Top Sealing |
Delayed until next FY |
N/A |
2017-U13 |
Well No. 7 Rebuild |
Well work is complete. The motor is on order. |
|
2017-U15 |
Replace Two Fire Hydrants Behind Mason Plaza |
Work scheduled for spring construction |
|
2017-U16 |
Cathodic Protection for Ground Storage Tank |
Planning stage. |
|
2017-U17 |
High Service Pump No. 1 Rebuild |
In progress |
|
2017-U18 |
Replace Chlorine Analyzer |
Complete |
Aug |
2018-U35 |
BS&A Work Order Application |
Award of project anticipated in Feb/March to coordinate with other BS&A projects |
|
2018-U36 |
Sewer Push Camera Replacement |
Complete |
Nov |
2018-U37 |
Log Jam Removal Sycamore Creek |
Complete |
Nov |
PARKS/ CEMETERY/ FORESTRY/ NONMOTORIZED (P) |
|
||
2017-P8 |
Laylin Park Improvements |
Staff is evaluating final work priorities for the spring. |
|
2018-P1 |
Howell Road - Hayhoe Riverwalk (Dart Trailhead) |
Complete |
Nov |
2018-P2 |
Howell Road - Hayhoe Riverwalk Trail Extension |
Complete |
Nov |
2018-P3 |
Planning: 5 yr Parks/Recreation Plan; Bond Park Improvements |
In progress |
|
2018-P5 |
City Tree Evaluation |
Staff reviewing bids. |
|
MOTOR VEHICLE POOL (MVP) |
|||
2017-MVP6 |
1/2 Ton 2x4 Pickup Truck |
Complete |
Sep |
2017-MVP7 |
Mower |
Complete |
Jul |
2017-MVP8 |
Police Cars |
Delivered, starting to build |
|
2017-MVP9 |
Large Items (Leaf Vacuum) |
Complete |
Nov |
2017-MVP10 |
5-yard Dump/Plow Trucks |
Cab/Chassis Ordered |
|
2017-MVP18 |
Command Vehicle |
Complete |
Oct |
2017-MVP30 |
Front End Material Loader |
Complete |
Nov |
BUILDING, PROPERTY, EQUIPMENT (B) |
|||
2017-B1 |
Library- Facility Evaluation |
In progress |
|
2017-B3.1 |
Police: Portable Radios |
Complete |
Oct |
2017-B4 |
City Hall Landscaping and Lighting |
Phase 1 completed. Phase 2/3 scheduled for the spring as time and budget allows. |
|
2017-B6 |
Fire: Fire Engine 809/Tower 808 |
Pre-construction meeting scheduled for January 21 |
|
2018-B4 |
IT: BS&A Timesheet Program |
Not started, connection issues with offsite facilities |
|
2018-B4 |
IT: BS&A Cemetery and HR Upgrade |
Complete |
Nov |
2018-B6 |
IT: AV Room Technology Patch |
Evaluation is complete; staff are reviewing |
|
2018-B7 |
Planning: Cedar/127 Corridor (Transportation and Land Use) |
Moved to 2019-2021 – integrate with master plan |
|
2018-B24 |
City Hall Rental Space Furniture Replacement |
Old rectangle tables have been replaced with plastic ones. New chairs are currently being evaluated. |
|
Status of Current City Projects